Project Description: A section of Taylor Road in Loomis that will be resurfaced, sidewalks added and the bike trail extended.
Timeline: Construction 91 days Mon 6/8/20 Mon 10/12/20
Upcoming work – Loomis Downtown Plan Phase 3 Update
Week ending 6/26
Taylor Road from Horseshoe Bar to King Road (Taylor’s side of the road)
- Earthwork for new sidewalk
- Taylor Road at Loomis Grammar School
- Earthwork for new pedestrian crossing ramp
- Lanes will remain open in both directions
Week of 6/29-7/3
Taylor Road from Horseshoe Bar to King Road (Taylor’s side of the road)
- Preparation and placement of new sidewalk
- Taylor Road at Loomis Grammar School
- Preparation and placement of the new ramp
- Taylor Road from Del Oro High School to the Town Limit (Del Oro HS side of the road)
- Demolition and earthwork along the entire stretch.
- Lanes will remain open in both directions