Upcoming Work Newsletter 7/23/17

UPCOMING WORK
Concrete forming and placement will occur next week throughout the site on the West side of Taylor Road.  Grading work in preparation will continue prior to each phase of concrete placement.  Water service installation between Walnut and High Hand will continue and near completion next week.
 
LANDSCAPING PLANS
A separate project is planned to go to construction this year that will plant landscaping in the new planters. The current contractor is installing the underground irrigation mainlines so that the street and sidewalk will not be cut or disturbed with the landscaping project.
Every Thursday morning at 8am the Town hosts an open meeting at the Loomis Train Depot