Update July 14, 2017 – Concrete Work

CONCRETE WORK
Progress was made on concrete sidewalk placement during the last
week, however, the concrete work is lagging behind the earth work.
This has been a busy summer for construction in the area and
concrete crews are in high demand. We are optimistic that next week
the Contractor will be able to place a significant amount of concrete
on the entire West side of Taylor. The specialty stamped red brick
concrete bands in the sidewalk are taking longer than anticipated to
prepare and it make take a few weeks for that work to begin.

Newsletter 2017-07-14